HVAC Training
Page: 10 of 13
Title: Chiller High Voltage Motor Terminations Lesson Plan #: NMH30L050303
EO 1.1.2 Install a high voltage chiller motor terminal assembly.
1.1.2.1 Introduction
In this objective the trainee will perform the procedure for installing the motor terminal assembly on 19FA Carrier
Centrifugal Chillers.
1.1.2.2 Methods and Activities
Refer to the applicable vendor documents.
1.1.2.3 Main Idea
Although there are currently three styles of high voltage terminal assemblies used on our 19FA
chillers, the ceramic style is the only one available for replacements.
Before using the replacement kit, check the VTD to ensure you have the correct kit needed for your
application. And to make sure all parts required are included in the kit.
Be sure to carefully read and understand the installation instructions before starting the installation.
1) Installation Instructions for the ceramic terminals.
To ensure a leak tight seal, the motor end terminal board mating surfaces must be clean and
smoothly coated with epoxy paint which has had sufficient time to cure dry.
a) Lightly lubricate quad ring (Parker Super Lube) or approved vendor lube. Install in terminal
board groove. Slide assembly over motor lead.
b) Install terminal board to motor shell with bolts and washers and evenly tighten bolts to
approximately 5 ft lbs.
c) Then torque bolts to 12-15 ft-lbs in a sequence As shown in the VTD or vendor supplied
instructions. Users of M&TE, ensure M&TE calibrations are current as specified on the
calibration label, we are responsible to ensure calibration is current. We are responsible to
ensure M&TE is within its restricted usage criteria.
i) Take note that new bolts are included to accommodate the "thickness of the new
aluminum terminal board compared to the old plastic type terminal board. (the new bolts
are shorter)
d) Install o-ring on ceramic insulator.
e) Lubricate ceramic insulator o-ring and mating surface with o-ring lubricant.
f) Slide terminal stud into ceramic insulator.