Chiller Maintenance
Lesson Plan
#:
NMH30C000105
elapsed from the time of notification by the HVAC group to the actual start of disassembly.
Based on the information received from the HVAC mechanic, the I&C technician did not check
the freon pressure gage. The technician was loosening the bonnet bolts for the jet pump
solenoid valve on "C" Chiller when freon started spraying from the opening. The technician and
the chiller w ere sprayed before he managed to reassemble the solenoid valve sufficiently to
stop the leak. The HVAC group was informed and they reduced freon level and pressure to
allow work to continue. A small amount of freon was expelled during subsequent disassembly
but the technicians were prepared for it and consequently it was not a problem.
2) Why did it happen? The causes identified in the OE
1. The I&C technician did not perform the task immediately upon isolation of the system.
When the HVAC mechanic notified I&C, he did not communicate that the internal pressure
would increase with time. The technician did not know the internal pressure would increase
with time as the chiller heats up from the initial cool down.
2. This critical information was not covered in the pre-job briefing. The I&C technician did not
communicate with the HVAC mechanic just prior to removing the solenoid and was not
expecting freon to spray out when the solenoid w as removed.
3) Could this type event happen at PV? What scheduling problems can the group identify
that may be applicable?
Corrective actions identified in the OE.
The I&C and Mechanical HVAC maintenance groups have discussed communication protocol
and awareness of possible changing conditions on plant equipment when delays in work
activities occur or time is of the essence. In the future HVAC and I&C will work together on this
task until the solenoid is removed. Additional means to isolate the system or a way to note the
potential for freon leakage during task performance is being investigated by maintenance.
4) What could you do to prevent this from happening?
Explanation
Have the students look at the Essential PM as you cover the lesson.